Timeline

The project will adhere to the following, preliminary schedule.

 Begin design phase.
08 / 27 / 2008Preliminary meeting and outline of site needs and requirements.
Begin development of survey questionnaire and card sorting items.
09 / 01 / 2008Administer surveys and card sorts.
09 / 05 / 2008Gather design guidelines and rubric choices from surveys, begin evaluating data.
09 / 12 / 2008Finish analyzing data. Begin development of project documentation.
Design initial site layout and concepts.
09 / 19 / 2008First inception of Low Fidelity prototype. Applied to Human Studies.
 Begin evaluation phase.
09 / 19 / 2008Last date to receive approval from IRB/HSC for testing.
09 / 26 / 2008Test and Evaluate first iteration of low-fidelity prototypes.
10 / 10 / 2008Finish re-designing of prototypes on basis of preliminary findings.
10 / 17 / 2008Test and Evaluate second iteration of low-fidelity prototypes.
10 / 31 / 2008Finish re-designs of prototypes. Begin high-fidelity prototypes.
11 / 07 / 2008Finish development of high-fidelity prototypes.
Reapplied to Human Studies.
11 / 14 / 2008Testing with Eye Tracking equipment of high-fidelity prototypes.
11 / 28 / 2008Thanksgiving Recess
12 / 05 / 2008Complete evaluation of data from high-fidelity prototypes testing.
12 / 19 / 2008Project Deadline – Final Report Due.